Party Wall Advice

Whether you’re a building owner about to undertake a building extension project, or your neighbours have just let you know that they plan some work that you think may have an impact on your property, we are here to provide all the help and advice you will need for following the Party Wall Act 1996.

Our RICs and FPWS qualified surveying consultants aim to make the process as seamless as possible and provide guidance throughout.

The Act was established to provide a framework for preventing or resolving disputes related to party walls, party structures, boundary walls, and excavations near neighbouring buildings. If you're planning to carry out work that is considered notifiable under the Act, building owners must give the adjoining owners notice of their intentions.

What is the Party Wall Act?

What is a Party Wall?

In simple terms, a "party wall" is a wall that divides two properties. A party structure could be a ceiling or floor that separates properties such as flats and a party fence wall is a boundary wall astride the line of junction. In addition, if you’re digging foundations, you’ll need to be more than 3 meters from your neighbour’s property. Building work that affects any of these is likely to need to issue Party Wall Notices.

Use our guide below to check if you think you need to serve notice or simply give us a call for some free advice.

Party Wall Act Guide

Building Owner Serves Notice on Adjoining Owner



Neighbour Consents

Serve 10 Day Notice

Adjoining Owner Responds within 14 Days

No Response within 14 Days of Notice

Appoints Same Surveyor as Building Owner



Appoints Own Surveyor

Neighbour Dissents and Requests an **Award

The Act does not apply


*Schedule of Condition Advised

Commence Works

If No Response, you can appoint a surveyor to represent the interest of the Adjoining Owner



Both Surveyors Liaise & Appoint a Third Surveyor in case of Dispute



*Schedule of Condition Conducted

Award Drafted, Negotiated & Served

Commence Works

*Schedule of Condition: Photographic report of the adjoining owner’s property prior work commence.

**Award: A detailed contract outlining details of the work, method statements and precautions in place.

What do Party Wall Surveyors do?

Our experienced team will look over your plans, check the notices if you have issued yourself and may ask for more details or clarification to make sure that the work is unlikely to cause damage to your neighbour’s buildings.

If a schedule of condition is required, the surveyor will visit your neighbour’s property and conduct a survey of current condition of the neighbouring property where works may have an impact and produce a visual report so that it can be referred to should any damage be caused as a result of the work.

Should a more detailed document in the form of a Party Wall Award be required, our surveying team will not only undertake the schedule of condition but also draft or negotiate with other appointed surveyors an agreement of the works. This will set out the works that are authorised and what happens if something were to go wrong. It is a binding, legally enforceable agreement.

The Award covers the work to be undertaken, method statements, access rights, working hours and other details covering the build such as damages. It can also cover the need for financial security, what will happen if damage is caused and will deal with any costs, including surveyors’ fees. In most cases the building owner undertaking the work will be responsible for surveying costs.

In very unusual circumstances, if the surveyors cannot agree, they will refer the matter to a ‘Third Surveyor’ for arbitration. The third surveyor will prepare and serve a binding party wall award.

Get professional advice

Our specialist team understand the Party Wall Act inside out and are here to answer your questions and guide you through the entire process. See our Q&A section below for further detail on serving notices or alternatively, get in touch to see how we can help you.